https://origsvn.digium.com/svn/asterisk/branches/1.8
................
r281575 | russell | 2010-08-10 13:05:07 -0500 (Tue, 10 Aug 2010) | 16 lines
Merged revisions 281574 via svnmerge from
https://origsvn.digium.com/svn/asterisk/branches/1.6.2
........
r281574 | russell | 2010-08-10 13:04:32 -0500 (Tue, 10 Aug 2010) | 9 lines
Don't move the time threshold for running scheduled events on every iteration.
Instead, only calculate the time threshold each time ast_sched_runq() is called.
(closes issue #17742)
Reported by: schmidts
Patches:
sched.c.patch uploaded by schmidts (license 1077)
........
................
git-svn-id: https://origsvn.digium.com/svn/asterisk/trunk@281576
65c4cc65-6c06-0410-ace0-
fbb531ad65f3
ast_mutex_lock(&con->lock);
+ when = ast_tvadd(ast_tvnow(), ast_tv(0, 1000));
for (numevents = 0; (current = ast_heap_peek(con->sched_heap, 1)); numevents++) {
/* schedule all events which are going to expire within 1ms.
* We only care about millisecond accuracy anyway, so this will
* help us get more than one event at one time if they are very
* close together.
*/
- when = ast_tvadd(ast_tvnow(), ast_tv(0, 1000));
if (ast_tvcmp(current->when, when) != -1) {
break;
}